Project Description
Due to the growing needs in York County, a new transmission line approximately two miles in length will be constructed in the India Hook area. Central Electric Power Cooperative, Inc. (Central) is responsible for working with your local energy cooperative to provide you with reliable power and will be completing this necessary project.
To complete this project, the line route must first be decided. This decision process involves community input and objective criteria to decide a route that minimizes social and environmental impacts while meeting the engineering, construction, and maintenance requirements. The project will not impact your current power or billing, but will still better serve your future energy needs by enhancing the reliability of the electric service in the area.
For more information please read through the rest of the material on this webpage, including the attached pdf handouts at the bottom of the page.
Hotline Information
Contact Central about this project through email or call the automated voice messaging system. A staff member will respond to you within two business days.
Email: indiahook@cepci.org
Call: 803-888-1060
Project Timeline
Project Kickoff: Summer 2021
Siting Study: Summer 2021
Open House and Stakeholder Survey: Fall 2021
Selection of Final Transmission Route: Fall 2021
Land Acquisition: Winter to Fall 2022
Vegetation Management: Spring 2023
Construction Start Date: Winter to Spring 2023
Completion Date: April 2023
Interactive Map
Being able to see the project route options in an interactive way can help make more sense than a flat piece of paper. Click the provided link to go to an interactive map – allowing you to view the project area, including the ability to search for and view your property location or other areas of interest in proximity to the project.