Project Description
Due to the growing needs in Jasper County, a new transmission line approximately two miles in length will be constructed in the Hardeeville area. Central Electric Power Cooperative, Inc. (Central) is responsible for working with your local energy cooperative to provide you with reliable power and will be completing this necessary project.
Project Timeline
Project Kickoff: Winter 2022
Siting Study: Winter 2023
Open House and Stakeholder Survey: Spring 2023
Selection of Final Transmission Route: Spring 2023
Land Acquisition: Fall 2023
Vegetation Management: Spring 2024
Construction Start Date: Summer 2024
Completion Date: Fall 2024